Rodboro Street, Parkhurst (McKean Street to Water Street) - Roadworks

  • Project typeRoadworks
  • Project scheduleWorks are scheduled to commence Monday, 26 May 2025 and are estimated to take approximately four (4) months to complete, subject to weather and ground conditions.

Roadworks are about to commence along Rodboro Street from McKean Street to Water Street, Berserker. The scope of works includes constructing a 1.5 metre-wide concrete footpath, widening sections of the road, reconstructing kerb and channel, installing rubber roundabouts and concrete traffic islands, and providing associated signage and line marking.

 

 

 