Haynes Street & Main Street, Park Avenue - Roadworks

  • Project typeRoadworks
  • Project scheduleWorks are scheduled to begin on Sunday, 21 September 2025 and are expected to be completed by March 2026, subject to weather and ground conditions.

Road reconstruction works are about to commence in Park Avenue, including: 

• Haynes Street from Main Street to Park Street 

• Main Street from Haynes Street to Edgar Street 

Works will include stormwater upgrades, kerb and channel replacement, footpath replacement, water main replacement, pedestrian crossing upgrade, asphalt overlay and line marking.

Stage 1 - Haynes Street (Main Street to Park Street)

Stage

Dates

Hours

Days

Traffic Impacts

1A

21 Sep – 4 Oct

6:00am – 12:00am

Sun–Fri

Full road closure 24/7; detours; resident access only

1B

4 Oct – 19 Oct

6:00am – 5:00pm

Mon–Fri

Half road closure during work hours; detours

1C

19 Oct – 31 Oct

7:00pm – 5:00am

Sun–Fri

Half road closure during work hours; detours

1D

Asphalt Overlay & Linemarking

To be confirmed

To be confirmed

Road closure; detours

 

Stage 2 - Main Street (Haynes Street to Pedestrian Crossing)

Stage

Dates

Hours

Days

Traffic Impacts

2A

19 Oct – 28 Nov

7:00pm – 5:00am

Sun–Fri

Half road closure during work hours; detours; parking restrictions

2B

6 Dec – 23 Dec

6:00am – 3:00pm

Sun–Fri

Parking restrictions only

2C

Asphalt Overlay & Linemarking

To be confirmed

To be confirmed

Road closure; detours

 

Stage 3 - Main Street (Pedestrian Crossing to Edgar Street)

Stage

Dates

Hours

Days

Traffic Impacts

3A

5 Jan – 25 Jan

6:00am – 3:00pm

Sun–Fri

Parking restrictions only

3B

1 Feb – 14 Mar

7:00pm – 5:00am

Sun–Fri

Half road closure during work hours; detours

3C

Asphalt Overlay & Linemarking

To be confirmed

To be confirmed

Road closure; detours

 

 

 

 

Location

Haynes Street, Park Avenue 4701  View Map