Callan Street, Wandal – Roadworks

  • Project typeRoadworks
  • Project scheduleWorks are scheduled to commence Monday, 2 February 2026 and are estimated to take approximately three (3) working weeks to complete, subject to weather and ground conditions.

Roadworks are about to commence in Callan Street, Wandal in front of properties at 2, 4, and 6 Callan Street. The works to be undertaken will include excavation and replacement of a short section of kerb and channel, and the removal and reconstruction of three concrete driveways.

 

 

 

 