GSTP - SRSTP Diversion Pipeline

  • Project typeSewer Rising Main and Effluent Main Construction Works
  • Project scheduleFitzroy River Water (FRW) is undertaking major underground sewer infrastructure works across multiple locations as part of the GSTP-SRSTP Diversion Pipeline Project. Works commenced in November 2024, and the majority of high-impact construction activities have now been completed, with the remaining works continuing through to late 2026.

The project involves the construction of approximately 8.6 kilometres of new 375 mm ductile iron cement lined (DICL) sewer rising main between the South Rockhampton and Gracemere Sewage Treatment Plants, along with a new 250 mm treated effluent main that will connect to the existing effluent network in the future. 

Due to the length and nature of the project, construction activities will progress through different locations in stages as work fronts advance.  

The majority of pipeline installation works have now been completed.  As the project moves toward completion, remaining construction activities will largely occur within easements and road reserves, resulting in minimal impacts to the public and road users.

Location

Fairy Bower &, Port Curtis 4700  View Map

Google Map