Plahn Street, Frenchville - Stormwater Works
Announcement
Stormwater works have commenced in Plahn and Berserker Streets.
- Project typeStormwater Works
- Project scheduleWorks commenced on Thursday, 19 November 2026 and are estimated to take approximately twenty-four (24) working weeks to complete, subject to weather and ground conditions.
Stage One: (approx. 6 weeks)
Scope of works: Install stormwater pipes and connect to existing manhole at 116 Plahn Street.
Traffic Impacts: The works will take half the width of the street between number 116 and Berserker Street. Access to residents will be maintained with traffic controllers in place during working hours.
Stage Two: (approx. 18 weeks)
Scope of works: Install stormwater pipes and manholes, construct sections of new kerb and asphalt surfacing to the work area.
Traffic Impacts: Berserker Street will be closed to through traffic between Kerrigan Street and Cruikshank Street, in addition, Plahn Street will also be closed between Brigg Street and Berserker Street. Access for residents will be maintained with traffic controllers in place as required.
Please note, there will be no access to Berserker Street from the Kerrigan Street roundabout. Local traffic will be required to enter from the northern (Cruickshank Street) end. Local traffic will only be able to exit onto Kerrigan Street.
Parking and speed restrictions will also be in place at various times during the works.
Council requests that drivers exercise caution during these works, obey all signage and do not park vehicles on the road whilst the works are being undertaken.