Norman Road and Foulkes Street Intersection, Norman Gardens - Roadwork

  • Project typeRoadworks
  • Project scheduleWorks are scheduled to commence Monday, 28 September 2026 and are estimated to be complete in August 2027, subject to weather and ground conditions.

Announcement: The works will be carried out over three stages, with dates subject to change: 

Stage one – September 2026 until February 2027: Works on the western (CQU side of Norman Road. 

Norman Road and Foulkes Street will be open, with speed reduced to 40km/h. 

Stage two – February 2027 until June 2027: Works on the eastern side of Norman Road. Norman 

Road will remain open with speed reduced to 40km/h, with the Foulkes St intersection closed. A detour 

will be in place via Springfield Drive and Nagle Drive. 

Stage three – June 2027 until August 2027: Works in the centre median. The inbound lane of Norman 

Road will be closed at the Yeppoon Road intersection with a detour in place via Yaamba Road and River 

Rose Drive. Foulkes Street intersection will remain closed.  

 

Location

Norman Road and Foulkes Street Intersection, Norman Gardens, Norman Gardens 4701  View Map

Google Map