Macquarie St between L59 and Middle Rd Gracemere - Reconstruction

  • Project typeReconstruction
  • Project scheduleCommencing mid Late September 2020 and is estimated to be completed by Mid April 2021 (subject to weather and ground conditions)

The project is a continuation of the works which were carried out in Macquarie Street, from Foster Street to Douglas Street, April 2020. 

The road works will include the widening and strengthening of existing pavement, the construction of kerb and channel, and the installation of a box culvert creek crossing. Asphalt surfacing and concrete driveways will also be installed as per the previous stages.

During this time Macquarie Street will be closed to through traffic, between Middle Road and Douglas Street for the duration of the works, although access will be maintained for local residents and businesses. All other traffic will be detoured via Middle Road, Capricorn Street and Foster Street, Gracemere.

Council requests that drivers exercise caution during these works; obeying all signage, and to not park vehicles on the road whilst the works are being undertaken.

 

 

Contact details

Jason Pierce
(07) 4932 9000 or 1300 22 55 77

Location

Macquarie Street, Gracemere 4702  View Map

Google Map