Farm Street and Alexandra Street - Reconstruction Works - Stage 3

  • Project typeReconstruction
  • Project scheduleWorks will continue until the end of May 2023.

Farm Street and Alexandra Street - Reconstruction Works - Stage 3

Stage 3 commenced on Saturday, 25 February 2023.

Temporary traffic conditions during Stage 3 include:

  • Alexandra St will be closed to northbound traffic between Farm St and 204 Alexandra St.
  • Traffic Lights at the intersection of Farm and Alexandra St will be back in operation.
  • Southbound traffic is permitted through the worksite.
  • Detour route for northbound  vehicles is via Quinn St / Maloney St
  • Northbound heavy vehicles detoured via Farm St / Yaamba Rd / Boundary Rd / McLaughlin St / Johnson St
  • The detours will be in place 24 hours a day while the work is underway.
  • Access to businesses within the work area will be maintained at all times
  • No on-street parking within the work areas.

Works on this stage are expected to be completed by the end of May 2023 subject to weather and ground conditions. 

If you have any questions or concerns, please do not hesitate to call 4932 9000 or email FarmStProject@rrc.qld.gov.au.  

Updated Stage 3 Temporary Traffic Changes(PDF, 678KB)